Weakly Report 5th April 2002

of the National Consultant (NC) from Hungary

”Preparatory Project for the Tisza River Basin Sustainable Development Programme (TRB-SDP)”

(December 2001-April 2002)

 

1.      Provisional identification of the potential national key interests in the TRB-SDP

a.) Analysis of the main public sources of information on the national part of the TRB (the Internet, recent newspapers, etc.)

 

During winter time (December - March) the weather in different periods is likely to be somewhat milder and rainy. The risky factor is that in watershed area of River Tisza the water content of the accumulated snow amount.

On the territory of Hungary in the region of the Upper-Tisza the dikes were reinforced on a lenght of almost fourty km, but the embankments on certain regions are not built yet.

That is the reason why the population living along the River Tisza always focusing on the changing.

Newspapers and electric journals follow the stage of sense of people.

 

b.)    Provisional personal consultations with the experts

 

Hungarian National Commitee of CEMAT – COE (European Conference of Ministers Responsible for Regional Planning of the Member States of the Council of Europe) gave information about the Draft Agreement on the Sustainable Spatial Development of the Tisza / Tisza River Basin

Hungarian National Representatives are the next:

                        Ministry of Transport and Water Mng: Mr. Tamás Kőszegi

                                                               1077 Budapest, Dob utca 75/81.

                                                               Tel: 322-0220

                        Ministry of Environment: Ms. Zsuzsa Árokháti

                                                               1011 Budapest, Fő utca 44-50.

                                                               Tel: 457-3300

                        Ministry of Agriculture and Regional Development: Mr. Károly Misley

                                                               1055 Budapest, Kossuth tér 11.

                                                               Tel: 301-4000

to the top

2.      Networking (December 2001 – February 28, 2002)

a.) Identification of the most important organisations / contact persons relevant for the       identification of  potential national investments needs and priorities (on the Tisza catchment) for the TRB – SDP (concerned ministries, local governments, academic institutions, regional organizations).

 

     

 

 

b.)               Presentation of the concept of the TRB-SDP, and the role of the current project, via telecommunication and in personal meetings to the contact persons

 

In the recent years, the Tisa/Tisza river basin has come to the forefront of international attention due to a sequence of major flood events and environmental disasters. Tisa/Tisza together with its tributaries drains the largest catchment area in the Carpathian Mountains before flowing through the Eastern Pannonian Plain and joining the Danube. The river and its catchment is shared by five countries: Hungary, Romania, Slovakia, Ukraine and Yugoslavia. The countries and regions in the Tisa/Tisza river basin share a common recent history of communist controlled systems and teh transition towards democracy and market economy in the last decade. This history has left the river basin with a mixed legacy of pollution hot spots, declining heavy industry, lack of economic development, emerging pattern of regular flooding and fertile ground for social and ethnic tensions on one hand, and with well preserved traditional rural landscapes, vast complexes of natural forests and viable populations of species that are no longer present in Western Europe on the other hand.

The Programme should encompass the entire geographical area of the Tisa/Tisza river basin including the natural resources and ecosystems, the entire economy and social groups. The relevant institutions and organizations in the five countries already have informations about the situation and ideas of future development. In such situation the most appropriate method to develop a comprehensive programme is to use the process approach, inviting all the relevant stakeholders to provide their input, based on common understanding of the situation, problems and options for the future.

 

            Dr. Attila Kemény

            State Secretary (Ministry of Environment) was informed.

Regional Environmental Directorates are ready to participate in preparing of phisibility study of the projects.

 

Dr. Péter Szaló

Deputy State Secretary (Ministry of Agriculture and Regional Development) also welcomed the initiation and suggested to make tight contact to county Developement Associations.

 

c.)                Organisation of the national workshop(s) of the representatives of potential stakeholders (supported by REC on NGOs’ level).

 

Three national workshops are planned. The first one was organised 15-17. 02. 2002. parallel

            with Meeting of National Nature Conservation Board in Szarvas NGO’s were informed by experts about the challenges of our programme.

            Second one will be organised in Tiszadob in Upper-Tisza District 05. 03. 2002.

            Detailed program were preoared bz contribution of REC-Hungary.

            The third occasion 11. 03. 2002. will touch the Lower-Tisza district because itwill be organised in Szeged

First Workshop:

Date: 15-17. 02. 2002.

Venue: Szarvas

Participants: 60 persons

This workshop was organized with the Meeting of  National Nature Conservation Society

Program:

            János Zlinszky: Goals of Tisza River Sustainable Development Programme

            Ferenc Ligetvári: Watercatchment Development on based of ecological view

            István Nagy: New Vásárhelyi Plan

            József Hamar: Declaration about Tisza’s watershed

to the top

MAIN ESTABLISHMENTS

I.                   International relationship

1.      There will be very important to make tight cooperation among the five countries on the field of political intend and responsibility.

2.      Financial support and integration from EU are basic facilities to realize the regional development

3.      NGO’s activity – from the five countries – will help stakeholders to get basic information about ecological life and valuenof the Tisza water catchment.

 

II.                Government activities

1.      Harmonization of  priorities

2.      Multipurpose utilization

3.      More space for Tisza’s water body

 

Second Workshop:

            Date: 04-05. 03. 2002.

            Venue: Tiszadob

            Participants: 40 persons

            Program:

                        Ferenc Ligetvári: Goals of Tisza River Sustainable Development Program

                        Károly Misley: Participation on the First meeting of  CEMAT-CoE Meeting

(Draft Agreement on the Sustainable Spatial Development of the Tisa/Tisza River Basin  - Strasbourg)

József Várady: Waterworks among Tisza River

Balázs Nácsa: Organization of Tisza Association

Benő Horváth: Development and changing of Tisza River’s Landscape

 

MAIN ESTABLISHMENT

I.                   International relationship

1.1.     There is international background of integrated and complex thinking on sustaianable development

1.2.     The Conference of Ministers Responsible for Regional Planning of the Members States of the Council of Europe (CEMAT-CoE) declared few principles. Most important of them are: Sustainablity and Cooperation.

1.3.     The Council of Europe would like to work on Tisa/Tisza River Basin Development Program as the first agreement of European Large Space Development. The Regional Planning of Tisa/Tisza River Basin will contain the general strategy of all sectors.

1.4.     The participants should find a common method for monitoring.

1.5.     The common financial facilities have not declared.

to the top

II.                Government activities

Water (Flood) Management

2.1.     Regulation of Tisa/Tisza River was realized on the idea of Pál Vásárhelyi civil engineer. The works were started in 1845.

In 1998, 1999, and 2000 there were katastrophic floods.

New Vásárhelyi Plan is prepared. Instead of embarkment-lifting reservoirs will be established and utilised. On Tisa/Tisza River Catchment Area there are 54 reservoirs with 2.3 billion m3  capacity. For flood management only 5 reservoirs with  0.654 billion m3 . On the Hungarian territory 14 reservoirs are planned for regulation of flodd peaks.

On the Hungarian Great Plain 400 settlements are located with 300 thousands properties and 1.5 million habitants.

2.2.     The inundation territories were not classified as environmentally sensible areas.

 

III.             Local activities

Model-area (Tisza Space, Tisza  Association)

3.1.     Oxbow utilisation permit is given from government to local government for fishing. Native fish species will be put.

3.2.     Wetland areas are developed by Phare grant.

3.3.     Thermal bathes need aid for modernization.

3.4.     The natural conservation is highly developed in some districts.

 

d.)               Identification of the NFP representative(s)

The NFP representative is Dr. Miklós Péter Varga who is member of the National Disaster Defence Directorate.

The Program Manager and the NFP representative have continuons contact of programme development

 

e.)                Identification of the possible partners (governmental, academia representatives/experts) for the final identification of the national investment needs and priorities in the TRB-SDP

Same institutions and persons as was given in 2. a.

 

f.)                 Identification of national participants for the closing international conference, assistance  to the organisation of the conference.

 

Representative of

Ministry of Agriculture and Regional Development (if it is possible Deputy   State Secretary)

                        Ministry of Transport and Water Management

                        World Wide Fund

                        University of  Debrecen

                                    Institute of  Environmental Management and Policy

                        Tisza Club

to the top

3.      Mapping (December 2001- March 2002)

a.)    Identification of the sectors relevant to the development of the TRB_SDP in Hungary

As it was given in 2. a.

 

b.)    Identification of potential information holders (institution, individuals on the level of government and academic institution) useful for the national part of the TRB-SDP – creation of the network database (institutions, individuals, contact data)

As given in 2. a.

Furthermore:

Water Work and Planning Stock Company

1142 Teleki B. u. 15/17.

Tel: 1/384-4224

 

c.)    Development of the structure/contents for the national meta.- database on the TRB-SDP – in cooperation with the other NC-s, REC and project management by January 24.

Hungarian version is hosted by REC

 

d.)    Collection of the opinions of experts about the most crucial data sources/events (e.g., on legislation documents, running plans), expressed during personal meetings or in correspondence.

The main pont of view is based on the New Vásárhelyi Plan (Flood Management) which is prepared a new paradigm. Instead of concentraling on embarkments’ lifting to establishing reservoirs on flood risky areas.

 

e.)    Collection of the meta-data relevant for the development of the TRB-SDP using the established network and the meta-database contents.

Hungarian Version is hosted by REC.

to the top

4.      Final identification of the national key needs/prioroties/conflicts of interest in the TRB-SDP (during the national workshop(s) before the closing international conference.

During the first national workshop NGO’s made protest some details of New Vásárhelyi Plan

 

5.      Contribution to the work of project management

a.)    Participation in and assistance to the international project coordination workshops.

Progress is continously done.

 

b.)    Providing the draft Hungarian country chapter for the final conference report.

After the third workshops on the basic of the participants’ openion the declaration was sent to the ministries.

 

c.)    Finalisation of the Hungarian country chapter according to the decisions of the March Conference

The active contribution from REC Hungary this chapter will be finilized on the openion of the different stakeholders

 

d.)    Providing the final document  (harmonise the final documents of the five riparian country) in Hungarian language.

The REC Hungary is continously makes presentation on the REC webside in Hungarian language

 

e.)    Contributing to the interim and final project reports to be sent  to UNDP.

With contribution of Project Manager and National Focal Point this chapter will be discussed and supported by openion.

 

 

Contributions to the project’s website

a.) Goals, scope, planned progress of the SDP in the national part

Different literature is selected and sended for NC’s getting new information about the subject.

 

b.)    Submission of general information on geographical location, natural resources, economy, culture, and environmental/social problems in the area. The suggested model-area (Tiszatér = Tisza space, Tisza Association) was caracterized and presented.

 

c.) Findings, documents, and recommendations of the closing conference in Hungarian